Timeline for outdoor classroom

ASAP              Top Soil to cover entire outdoor area
Dec. 1-7          Rough grade so it slopes away from building         
Dec. 8-14        Dig trenches for drainage and sprinkler system
Dec. 15-22      Install drainage and sprinkler systems (Need drainage system)
Jan. 3-14         Install walkways (pea gravel, flat stones, etc.?)
January            Install ponds and water features  (maybe just one large pond with waterfall)
January            Construct gazebo, trellis, and pergola
February          Install gardens
February          Install low voltage lighting
End of March  Ribbon cutting ceremony